Welcome to  ECOTONE, INC.


Home

Services

  • Environmental   Consulting
  • Environmental Construction
  • Forest & Wetland Mitigation
  • Stream Restoration
   ·Hydraulic Suction Dredge for Stream Restoration

Selected Projects:

  • Falling Spring
  • Little Pipe Creek
  • Little Bennett Creek
  • Western Run
  • Bon Secours
  • East Branch   Winters Run
  • Lowel School Stream
The Team
Links
Upcoming Events
Press Releases/Articles
What's New

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Location:

1204 Baldwin Mill Road Jarrettsville, MD 21084
Phone: 410.692.7500
Fax: 410.692.7503

 

 

 

 

Tributary to Little Bennett Creek

Damascus, Maryland


 

The Use of Native Materials for River Restoration in a Rural Watershed Project Constructed Fall of 1999.
 
 Sponsor
 The project was funded by the Montgomery County Department of Public Works & Transportation.
 
 Project Description
 The existing channel was located in a cattle pasture where grazing and hoof impacts resulted in an extremely degraded stream channel, which in turn impaired existing wetlands and water quality. A design was prepared to raise the invert of the existing stream to allow it to communicate with the surrounding floodplain, and to create and restore forested wetlands throughout the surrounding floodplain areas. Wetland sod along with river gravel and cobble were used to stabilize the restored channel. A diversity of bed material sizes was imported to provide a natural particle size distribution in the restored channel. The design profile included the creation of naturally sloping riffles and pools to mimic the profile undulations of a natural stream.

 

Construction
 
 The stream restoration portion of the project was designed by Scott McGill, and the wetland construction was designed by Jim Morris, both principals of Ecotone, Inc. Both project components were constructed by C.D. Davis Excavating.
 
Cost
 
 Costs associated with the stream restoration component of the project averaged $30.00 per linear foot of stream restored.

 
Phases of the Project
Stream Prior To Construction. Cattle pasture prior to wetland construction project. This area is now wetland cells 2 and 3. Photo taken 1998.
Cattle which are allowed access to the stream contribute to problems. Years of exposure to grazing cattle have led to an ecosystem in poor health.
The stream experienced high bank erodibility as a result of hoof impact. A stable stream channel was created by raising the invert of the channel.
Once native sod is placed along the banks the stream will be complete. A crossing was installed so that cattle would have access to the stream.
On site wetland sod was placed along the stream banks. Immediately Following Stabilization.
The new channel is stable; the sod mats provide good initial bank stability. The new channel several days after construction is complete.
Soft brush was used adjacent to the low flow channel to provide deep rooting stability. Cattle explore the new stream crossing.
Looking upvalley in October of 1999. Cell 5 is in foreground. Looking upvalley during construction, October 1999.
Nine months post construction vegetation is taking a strong hold along the stream banks. Eleven months post construction lush vegetation makes it hard to see the stream channel in this photo.
The stream creeps its way through the wetland plants. Restored stream looking upstream.
Wetland Cell number 5, summer of 2001.