Welcome to  ECOTONE, INC.


Home

Services

  • Environmental   Consulting
  • Environmental Construction
  • Forest & Wetland Mitigation
  • Stream Restoration
   ·Hydraulic Suction Dredge for Stream Restoration

Selected Projects:

  • Falling Spring
  • Little Pipe Creek
  • Little Bennett Creek
  • Western Run
  • Bon Secours
  • East Branch   Winters Run
  • Lowel School Stream
The Team
Links
Upcoming Events
Press Releases/Articles
What's New

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Location:

1204 Baldwin Mill Road Jarrettsville, MD 21084
Phone: 410.692.7500
Fax: 410.692.7503

 

 

 

 

 
Falling Spring Restoration at Quarry Meadow

 

    In August of this year Ecotone Inc., a Maryland-based environmental consulting firm that specializes in stream and wetland restoration, completed a unique spring creek restoration project to improve fisheries habitat. The “Quarry Meadow Project” of the Falling Spring Branch in Chambersburg Pennsylvania was designed to restore more than 3,000 linear feet of stream, nearly doubling the high quality trout habitat of the already nationally significant natural trout fishery waters.

     The Falling Spring Greenway, Inc. (FSG), a non-profit corporation dedicated to the restoration and conservation of the Falling Spring Branch, realized that due to cattle grazing, damming, and channelization, the Valley Quarry section of the stream had, over many years, degraded to the point that the shallow waters could not maintain an adequate flow, depth or temperature to maintain the trout population. Rod Cross, president of the local Trout Unlimited chapter and board member of the FSG said, “Streams sometimes widen by themselves, and in doing so become shallower. The flow is diminished and silt covers up the good breeding gravel that trout need. Basically the stream hasn’t changed its character on its own.” After previous attempts to improve the stream through the creation of deflectors and revetment areas had failed to achieve the desired results, it was clear that a much larger effort was required.

Goals

     The FSG set out on the project in 1998 in search of funding with the goal of restoring 3,000 feet of Falling Spring from an over-wide pond-like stream devoid of fisheries habitat to a faster, narrower and deeper channel with plenty of deep holes, bank cover, and woody debris for fish habitat. The specific objectives of the project were as follows:

• Narrow the spring channel 50 to 75% in over-wide reaches;
• Provide a more defined riffle-run-pool profile to diversify habitat
• Increase low flow velocities
• Increase pool depths
• Increase bank-side and in-stream overhead cover
• Restore and enhance adjacent riparian wetland habitat.

 Design

     In developing the design, a geomorphic assessment and survey of the project reach and reference reach was conducted to determine the appropriate dimension for the restored channel. Falling Spring Meadow, a reach of stream upstream of the project with excellent fisheries habitat and a healthy wild rainbow and brown trout population, was used as the reference reach. Various geomorphic parameters were measured on the reference reach such as cross sections of pools and riffles, channel profile, pool, riffle , and run slopes, pool lengths, and discharge. Dimensionless geomorphic ratios were calculated based on the reference measurements such as width/depth ratio, pool depth/average depth ratio, radius of curvature/channel width, and riffle slope to average slope. Discharge was also measured at both the reference and project reach.

     The hydrology of Falling Spring is dominated by a series of perennial springs and the flow of the stream is not affected by stormwater runoff. As a result, morphological relations based upon bankfull discharge were not applicable, nor was using drainage area to extrapolate the morphological data from the reference reach to the project reach. Discharge measurements were made at both reaches and the relative differences in discharge at each reach were used to develop a conversion factor to convert the dimensionless ratios from the reference reach into the range of acceptable morphological parameters for the project reach. The discharge at the reference averaged 10 cfs while the project reach, one half mile downstream, averaged 16.5 cfs.

     Rather than design with one engineered channel width and depth, the minimum, maximum, and average dimensions of the reference reach were used to allow for a range of channel dimensions on the design reach to provide aditonal diversity and improved aesthetics of the finished channel shape. The channel width of the existing channel ranged from 20 feet to 65 feet, with an average width of 34.2 feet. The proposed channel dimensions called for a width of 20 feet with constrictions as narrow as 5 feet in several areas to promote velocity acceleration and to maintain scour pools. Table 1 summarizes the channel characteristics and dimensions of the existing, proposed, and reference reaches.

Techniques and Structures

     Various habitat improvement structures were proposed in the channel, including roller eddies, converging rock clusters, double wing deflectors, and coarse woody debris (root wad). Structures were selected and designed based on their ability to promote velocity distribution through the channel that provided enhanced habitat for trout. Trout prefer holding cover where velocities are fairly low directly adjacent to higher velocity lanes where food is carried through from upstream. The trout lay in the low velocity areas but can easily dart into the higher velocity lane to feed. They also prefer these areas of “velocity diversity” near deep water and/or overhead cover.

     Converging Roller Eddy: The structure was designed to create velocity acceleration into a vegetated stream bank, creating diverse velocity distribution in the channel with high velocities directly adjacent to lower velocity vectors for optimal feeding and holding habitat. Between the rows of boulders, flow is accelerated, creating additional stream power to scour and maintain a deeper channel, providing additional depth. Vegetation is incorporated in the boulder rows to create a natural appearance and provide additional overhead cover.

     Converging Rock Clusters: This structure also creates velocity acceleration and is similar in design to a more traditional double wing deflector. A large boulder, or cluster of smaller boulders, are placed just upstream of the deflectors to create flow convergence between the wing deflectors. The increased velocities will maintain a deeper thalweg and scour channel. Vegetation in the form of wetland seed, sod matting, and woody transplants are proposed on top of these structures to create a natural appearance and hide the rock.

     Double Wing Deflector with Willow Transplants: Similar in design to the Converging rock clusters with boulder placement in the downstream scour hole to create feeding lanes and resting areas.

     Root Wad: Root wads, normally used as bank stabilization as part of a revetment, were proposed for the project as coarse woody debris. The existing channel had very little woody debris in channel because of a lack of upstream supply and few on-site sources. By emplacing root wads in the channel, velocity distribution was enhanced, and available habitat for benthic organisms was increased. Vegetation, in the form of live stakes, will be planted directly in the root wads to promote vegetative growth and overhead cover.

Construction

     The project, completed in approximately seven weeks, and had two phases. Phase one, the construction phase in which the stream was narrowed and structures were installed took about four weeks. Phase two, the dredging phase, in which a “venturri-system” suction dredge was used to remove excess silt from the stream, took about three weeks. The sequence of construction was as follows:

Phase I

• Install turbidity control measures to separate work areas from the main flow;
• Transplant willows and red twig dogwoods to the new streambank edge;
• Fill the desired area with 4”-12” clean stone utilizing low ground pressure dozers
• Excavators and loaders narrowing the stream from as wide as 65 feet to as narrow as 5 feet;
• Capture sod from wetland areas away from the stream and place it along the banks.
• Backfill over the stone with 3”-12”of topsoil;
• Seed and mulch the new banks with a temporary seed mixed with a slower germinating wetland seed mix.



     The stone was placed as a stable base for the soil. The sod transplants, placed with a tracked skid steer, provided instant native vegetation along the bank to prevent runoff from entering the stream. Along with narrowing the banks a large part of the construction was the installation of the habitat structures and the enhancement of the natural meander of the stream. These features will help the stream to maintain its improved flow and provide cover and habitat for trout. The transplantation of willow and dogwoods to the new bank will also eventually further improve the stability of the banks and provide overhead cover and food sources for the trout and shade to help the stream to maintain the cool, consistent thermal regime.

Phase II

     The dredging portion of the project was designed to remove as much of the excess silt as possible from the streambed. Rather than dredging the entire stream with heavy machinery during Phase I, a deeper narrower thalweg channel was dredged and was sized so that it will be maintained by the stream over time and will not fill in. The dredge was also used to clean out sediments in and around habitat boulders and the habitat structures. The 4” dredge, powered by a 23 horsepower motor set on a floating barge, was custom designed by Ecotone to move over 10 cubic yards of silt per hour. The silt removed from the streambed was pumped up on land and was graded into the surrounding areas and immediately seeded and mulched to prevent any further erosion. Through dredging Ecotone was able to increase the depth of the stream from as shallow as four to five inches to as deep as five feet in select reaches.

     As the design-build contractor, Ecotone coordinated construction and selected C.D. Davis Excavating, Inc. from Pylesville, MD, a contracting firm specializing in wetland and stream restoration construction, to provide grading and equipment services.

Funding

     To fund this project the Greenway was able to secure $121,000 from the Pennsylvania Growing Greener Program and $75,000 from the National Fish and Wildlife Foundation while contributing $15,000 of its own resources for the project. “This project would not have been possible without the national, and state government assistance as well as cooperation from local volunteer organization and corporations.” said Cross. The assessment, survey, design, 404 and state permitting totaled $51,000 while construction costs, includi8ng planting and construction oversight, totaled $ 160,000.

Challenges

     Challenges and problems encountered during construction included extremely soft soils in low area adjacent to the stream. This, combined with heavy rains in the beginning of the project, made it extremely difficult to transport stone to the fill areas along the stream. Having low ground pressure dozers and loaders was a necessity in the soft areas. Also, the extremely low gradient of the stream, approximately 0.0006, or 0.06 %, did not allow for major field changes from the design.

Results

     Successes from the project seem to be evident only days after construction was completed. Due to the narrowing of the stream, low flow velocities in the stream have increased from nearly 0 feet per second (fps) to over 3 fps in areas where habitat structures were installed. Already these increased velocities have scoured out holes more than four (4) feet in depth and rainbow and brown trout have been spotted colonizing these lunker holes only several days after they were created.

     Electro-fishing efforts performed by Pennsylvania Fish and Boat Commission in 1976 indicated biomass of rainbow trout and brown trout totaling 18.5 pounds/acre and a total of only 40 trout over 2,500 linear feet. A cursory electro-fishing effort in September of 2001 found only 2 brown trout in the reach. Falling Spring is regulated as a Heritage Angling area and is not stocked by the Pennsylvania Fish and Boat Commission in the project area. Increases in trout numbers in the restored project reach will result from re-colonization by the existing rainbow and brown trout population.

     The success of the project in reaching its original objectives other than design goals includes the following:

     Landowner support: Nothing is possible without the landowner’s support and permission. Valley Quarries, Inc. was cooperative and helpful throughout the duration of the project.

     Local involvement and support: The Greenway has worked closely with the Falling Spring Chapter of Trout Unlimited. The Greenway and Trout Unlimited have a long history of cultivating interest in the watershed and with its landowners. The organizations’ credibility and track record in the community was vital to the project’s success.

     Rigorous design: The design consultants for the project were involved in assisting the Greenway obtain funding for this project since 1996, much of the work in the initial stages performed on a pro-bono basis. The same consultants followed the project through construction. This brought continuity and consistency throughout the project and assured that the design was implemented as intended.

The Future

     Ecotone and the Falling Spring Greenway have also recently announced the approval of a $200,000 grant from the Pennsylvania Growing Greener Program for the restoration of three other sections of the Falling Spring. Design of these three projects, which fall under a watershed permit acquired by the Greenway are projected to begin in the spring of 2003.

     For more information on this project, contact Mr. Scott McGill, Principal and Restoration Specialist, Ecotone, Inc., at (410) 692-7500; 1204 Baldwin Mill Road, Jarrettsville, MD 21084,
www.ecotoneinc.com